Connecting Channel Dredging Work in Babek TNI Cakung Targeted to Be Completed in This Month
Reported by Nurito | Translated by Maria Inggita
Dredging work on connecting (Phb) channel along 1.5 kilometers on Jl. Babek TNI, Cakung Timur Urban Village, Cakung, East Jakarta was targeted to be completed by the end of this December.
Dredging can be only carried out to maximum 1-1.5 meters
East Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Head, Puryanto stated, from total length 1.5 kilometers, his side had dredged 1 kilometers or about 65 percent of the work.
"Our target is to complete it by the end of December," he asserted, Monday (12/6).
Rawa Malang Reservoir Development Progress Reaches 70 PercentAccording to him, mud dredging was carried out to overcome inundation that often occurs in TNI Babek Headquarter due to overflowing water from connecting channel.
For dredging the channel, his side deployed 2 heavy equipment, namely mini amphibious and large amphibious excavators.
"Initially, we plan to dredge the mud until 1.5 to 2.5 meters depth. However, because there are many factory fences around it, dredging can be only carried out to maximum 1-1.5 meters," he explained.